In an AOA network diagram, what occurs when two or more activities follow a single node?
A) combinations
B) buffers
C) mergers
D) bursts
Correct Answer:
Verified
Q53: Which dependencies involve relationships between project and
Q54: What term is used for the amount
Q55: Which provide a standard format for displaying
Q56: Which is true of dummy activities?
A) They
Q57: In project schedule management, the ultimate goal
Q59: After working with key stakeholders to define
Q60: Which dependencies are sometimes referred to as
Q61: _ have no duration and no resources
Q62: _ involves the processes required to ensure
Q63: After reviewing the project management plan, project