_____ have no duration and no resources but are occasionally needed on AOA network diagrams to show logical relationships between activities.
Correct Answer:
Verified
Q56: Which is true of dummy activities?
A) They
Q57: In project schedule management, the ultimate goal
Q58: In an AOA network diagram, what occurs
Q59: After working with key stakeholders to define
Q60: Which dependencies are sometimes referred to as
Q62: _ involves the processes required to ensure
Q63: After reviewing the project management plan, project
Q64: Which technique involves doing activities in parallel
Q65: Which law states that work expands to
Q66: In project schedule management, the process of