Which of the following is NOT true of activity slack?
A) It is the amount of time an activity may be delayed (from time of early start) without delaying the completion of the project.
B) It is also known as activity float.
C) It is calculated as LS - ES.
D) It is calculated as LF + EF.
Correct Answer:
Verified