If an estimate for an activity is deterministic,then ______.
A) sufficient historical information is available to make this determination with a reasonable degree of accuracy
B) the estimate is based on probability that the activity will be completed in a given time frame
C) the estimate is based on probability that the activity will be completed in a given time frame plus/minus three standard deviations
D) the estimate is based on a stochastic model
Correct Answer:
Verified
Q68: Which of the following is an appropriate
Q69: Which is the critical path in the
Q70: In managing projects in supply chains,working with
Q71: Which of the following is NOT true
Q72: The forward pass method allows us to
Q74: A merge point refers to _.
A)a node
Q75: Which of the following statements is FALSE
Q76: Which of the following is an activity
Q77: If an activity has 4 days of
Q78: To complete a project quickly,we should _.
A)crash
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents