If an activity has 4 days of slack,then ______.
A) a delay of 3 days will not have an impact
B) a delay of 5 days will not have an impact
C) a delay of 7 days will not have an impact
D) a delay of 9 days will not have an impact
Correct Answer:
Verified
Q72: The forward pass method allows us to
Q73: If an estimate for an activity is
Q74: A merge point refers to _.
A)a node
Q75: Which of the following statements is FALSE
Q76: Which of the following is an activity
Q78: To complete a project quickly,we should _.
A)crash
Q79: Labeling activity nodes in the network is
Q80: A critical path _.
A)is the longest individual
Q81: A line tracking the project costs over
Q82: The term greenwashing refers to _.
A)a superficial