Acme,Inc.,produces widgets.To manufacture a new type of widget,it took 56 hours for the first widget.Acme estimates it has an 89% learning rate.Using the logarithmic approach,calculate the time it will take to manufacture the 112th widget.
A) 29.35 hours
B) 25.37 hours
C) 31.27 hours
D) 29.94 hours
Correct Answer:
Verified
Q59: The first unit produced in a process
Q60: The first unit produced in a process
Q61: Acme,Inc.,produces widgets.To manufacture a new type of
Q62: Acme,Inc.,produces widgets.To manufacture a new type of
Q63: Acme,Inc.,produces widgets.To manufacture a new type of
Q65: Weston,Inc.,produces widgets.To manufacture a new type of
Q66: Weston,Inc.,produces widgets.To manufacture a new type of
Q67: Weston,Inc.,produces widgets.To manufacture a new type of
Q68: Acme,Inc.,produces widgets.To manufacture a new type of
Q69: Acme,Inc.,produces widgets.To manufacture a new type of
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents