Acme,Inc.,produces widgets.To manufacture a new type of widget,it took 51 hours for the first widget.Acme estimates it has an 85% learning rate.Using the logarithmic approach,calculate the time it will take to manufacture the 148th widget.
A) 16.24 hours
B) 15.86 hours
C) 19.52 hours
D) 16.94 hours
Correct Answer:
Verified
Q63: Acme,Inc.,produces widgets.To manufacture a new type of
Q64: Acme,Inc.,produces widgets.To manufacture a new type of
Q65: Weston,Inc.,produces widgets.To manufacture a new type of
Q66: Weston,Inc.,produces widgets.To manufacture a new type of
Q67: Weston,Inc.,produces widgets.To manufacture a new type of
Q69: Acme,Inc.,produces widgets.To manufacture a new type of
Q70: Acme,Inc.,produces widgets.To manufacture a new type of
Q71: Weston,Inc.,produces widgets.To manufacture a new type of
Q72: Acme,Inc.,produces widgets.To manufacture a new type of
Q73: Weston,Inc.,produces widgets.To manufacture a new type of
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents