Planned value is ______.
A) the total budget
B) a way to identify the expenditures at any one stage in the project
C) a cost estimate of the budgeted resources scheduled across the project's life cycle (cumulative baseline)
D) the real budgeted cost,or value,of the work actually performed to date
Correct Answer:
Verified
Q30: The SPI is _.
A)the stochastic performance index
B)the
Q31: The cost of the project is given
Q32: The work breakdown structure identifies _.
A)each of
Q33: Value generated by a project is _.
A)the
Q34: The time-phased budget _.
A)identifies the correct sequencing
Q36: Which of the following does NOT correctly
Q37: Which of the following statements is true
Q38: The work breakdown structure _.
A)identifies the individual
Q39: In calculating the probability of a project
Q40: The project's baseline _.
A)is the standard against
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents