Which of the following does NOT correctly pair the terminology used in the earned value management (EVM) method with its description?


A) planned value: a cost estimate of the resources used across the project's life cycle
B) earned value: the value of the work actually performed to date
C) actual cost of the work performed: the cumulative total cost of completing the project's work packages
D) budgeted cost at completion: the total budget for a project at its completion

Correct Answer: