Solved

If a Project Has an Expected Completion Time of 15

Question 41

Multiple Choice

If a project has an expected completion time of 15 weeks with a variance of 4 weeks,the probability that the project will be completed in 18 weeks is ______.


A) less than 34%
B) between 44% and 68%
C) between 69% and 83%
D) more than 93%

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents