If a Project Has an Expected Completion Time of 15

Question 45

Multiple Choice

If a project has an expected completion time of 15 weeks with a variance of 4 weeks,the probability that the project will be completed in 15 weeks is ______.


A) close to zero
B) half
C) more than 75%
D) less than 25%