If a project has an expected completion time of 15 weeks with a variance of 4 weeks,the probability that the project will be completed in 12 weeks is ______.
A) about 6.7%
B) about 43.3%
C) about 29.1%
D) about 54.3%
Correct Answer:
Verified
Q46: If a project is expected to be
Q47: If a project is expected to be
Q48: If a project is expected to be
Q49: If a project has an expected completion
Q50: The probability that a project will be
Q52: The normal activity duration of Activity X
Q53: Which of the following is NOT one
Q54: If a project is expected to be
Q55: If a project is expected to be
Q56: If a project is expected to be
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents