Solved

The Normal Activity Duration of Activity X Is 5 Weeks

Question 52

Multiple Choice

The normal activity duration of Activity X is 5 weeks and is budgeted to cost $12,000.The crash time for this activity is 3 weeks and is expected to cost $32,000.The cost slope for Activity X is ______.


A) $32,000 per week
B) $18,000 per week
C) $20,000 per week
D) $10,000 per week

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents