If a project is expected to be completed in 68 days with a project variance of 9 days,what is the probability that the project will be completed between 63 to 70 days?
A) 100%
B) 95%
C) 90%
D) 70%
Correct Answer:
Verified
Q52: The normal activity duration of Activity X
Q53: Which of the following is NOT one
Q54: If a project is expected to be
Q55: If a project is expected to be
Q56: If a project is expected to be
Q58: If project completion times are normally distributed,then
Q59: If a project is expected to be
Q60: The normal activity duration of Activity X
Q61: Find the area under the normal curve
Q62: Find the area under the normal curve