In Establishing the Project's Baseline,the Time-Phased Budget ______

Question 73

Multiple Choice

In establishing the project's baseline,the time-phased budget ______.


A) allows us to identify the correct sequencing of tasks
B) enables the project team to determine the points in the project when actual costs are likely to exceed budgeted costs
C) identifies the individual work packages and tasks necessary to complete the project
D) provides the managerial responsibilities for tasks in a project

Correct Answer:

verifed

Verified