Which of the following statements is FALSE with regard to costs of crashing activities in a project?
A) As each project activity is crashed in order,the overall project budget increases.
B) It is usually necessary to crash all activities in a project.
C) Crashing additional activities beyond a point merely adds costs to the budget.
D) It may not be possible to crash all activities in a project.
Correct Answer:
Verified
Q67: The most pessimistic time for a task
Q68: The most pessimistic time for a task
Q69: Find the area under the normal curve
Q70: A project's baseline represents _.
A)our best understanding
Q71: Find the area under the normal curve
Q73: In establishing the project's baseline,the time-phased budget
Q74: Find the area under the normal curve
Q75: Find the area under the normal curve
Q76: Find the area under the normal curve
Q77: Find the area under the normal curve
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents