The Most Pessimistic Time for a Task Is 28 Days

Question 67

Multiple Choice

The most pessimistic time for a task is 28 days.The most optimistic time for the same task is one fourth of the pessimistic time.Calculate the variance for the duration of the activity.


A) 8.75
B) 12.25
C) 14.85
D) 10.50