An activity was given a planned budget of $10,000.If 80% of that activity was completed,what was the resulting value?
A) $80,000
B) $8,000
C) $800
D) $80
Correct Answer:
Verified
Q59: If a project is expected to be
Q60: The normal activity duration of Activity X
Q61: Find the area under the normal curve
Q62: Find the area under the normal curve
Q63: Find the area under the normal curve
Q65: If the most optimistic and pessimistic times
Q66: Find the area under the normal curve
Q67: The most pessimistic time for a task
Q68: The most pessimistic time for a task
Q69: Find the area under the normal curve