If the most optimistic and pessimistic times for a task are 3 and 15 days respectively,then the variance for the duration of the activity is ______.
A) 3.00
B) 4.00
C) 5.00
D) 6.00
Correct Answer:
Verified
Q60: The normal activity duration of Activity X
Q61: Find the area under the normal curve
Q62: Find the area under the normal curve
Q63: Find the area under the normal curve
Q64: An activity was given a planned budget
Q66: Find the area under the normal curve
Q67: The most pessimistic time for a task
Q68: The most pessimistic time for a task
Q69: Find the area under the normal curve
Q70: A project's baseline represents _.
A)our best understanding
Unlock this Answer For Free Now!