The ______ is the relationship between two or more tasks that requires certain tasks to be done before others.
A) least priority relationship
B) precedence relationship
C) factor rating
D) contingency relationship
Correct Answer:
Verified
Q29: A line is said to be unbalanced
Q30: _ is the difference between the total
Q31: In line balancing,the desired cycle time (C)is
Q32: Which of the following methods is used
Q33: The letters on the Muther's grid indicate
Q35: _ is the measure of how well
Q36: In line balancing,the number of workstations required
Q37: Which of the following statements about creating
Q38: Which of the following techniques involves assigning
Q39: _ is the time required for the