In line balancing,the desired cycle time (C) is given by ______.
A) (Daily production time available) / (Units to be produced daily)
B) (Daily production time available) / (Number of workstations available)
C) (Units to be produced daily) / (Daily production time available)
D) (Total time used) / (Units to be produced daily)
Correct Answer:
Verified
Q26: The letter X on the Muther's grid
Q27: A _ is a tool for analyzing
Q28: Which of the following is NOT a
Q29: A line is said to be unbalanced
Q30: _ is the difference between the total
Q32: Which of the following methods is used
Q33: The letters on the Muther's grid indicate
Q34: The _ is the relationship between two
Q35: _ is the measure of how well
Q36: In line balancing,the number of workstations required