In a production process,the total time consumed by all tasks is 45 minutes.The total time available is 60 minutes.Given this information,which of the following statements is true?
A) The balance efficiency is 75%.
B) The balance inefficiency is 175%.
C) The balance efficiency is 25%.
D) The balance inefficiency is 125%.
Correct Answer:
Verified
Q83: If the sum of all task times
Q84: If the sum of all task times
Q85: If the sum of all task times
Q86: To calculate the theoretical minimum number of
Q87: The desired cycle time in a production
Q89: As real-life layout problems are typically large,we
Q90: As real-life layout problems are typically large,arriving
Q91: In process layouts,the process facilities are shared
Q92: Many commercially available computer packages such as
Q93: ALDEP is _.
A)used to balance asymmetric production
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents