In a production process,the total time consumed by all tasks is 300 minutes.The total time available is 270 minutes.Given this information,which of the following statements is FALSE?
A) The balance efficiency is .9.
B) The balance inefficiency is 10%.
C) The balance efficiency is 33%.
D) The balance inefficiency is 90%.
Correct Answer:
Verified