Which of the following describes how the team uses a cause-and-effect diagram to support project risk analysis?
A) The project team begins by identifying strengths, weaknesses, opportunities and threats.
B) The team organizes assumptions and constraints in a fishbone pattern.
C) The team lists the risk as the "effect" in a box at the head of a fish, then names the big bones.
D) Team members are encouraged to keep asking "when?" to break down risks into more detailed causes.
Correct Answer:
Verified
Q19: Sometimes the risks posed by a project
Q20: The risk register is a living document
Q21: On agile projects,detailed risk management activities may
Q22: Which of the following describes the activities
Q23: All of the following criteria can be