All of these describe contemporary methods of risk prioritization in project management EXCEPT:
A) Risk prioritization is generally based on the probability of occurrence and severity of impact of each identified risk.
B) Some organizations place a higher priority on risks that are likely to happen soon.
C) Some organizations call attention to the risks that are difficult to detect.
D) Results of quantitative risk analysis are used for clarification purposes and are typically not documented in the risk register.
Correct Answer:
Verified
Q24: Which of the following describes how the
Q25: Q26: All of the following are among the Q27: All of the following describe the appropriate Q28: Risk response strategies such as mitigation and Q30: All of the following methods have proven Q31: A _ presents a hierarchical organization of Q32: When a project team elects to purchase Q33: Project managers can identify risks by learning Q34: Which of the following activities illustrates a
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents