Which of the following activities illustrates a risk response strategy designed to mitigate a threat?
A) adopt a fixed price type contract
B) train a team member to cover for a potentially unavailable key resource
C) change the project plan or scope
D) develop change control procedures
Correct Answer:
Verified
Q29: All of these describe contemporary methods of
Q30: All of the following methods have proven
Q31: A _ presents a hierarchical organization of
Q32: When a project team elects to purchase
Q33: Project managers can identify risks by learning
Q35: All of the following describe an appropriate
Q36: Project teams can often identify risks by
Q37: Which of the following quantitative risk analysis
Q38: Which of the following accurately describes risk
Q39: All of the following are benefits that
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents