There are several conventions used to aid in estimating percentage completion.Which of the following is the most conservative?
A) 50-50 rule
B) 0-100 percent rule
C) Critical input use
D) Proportionality
Correct Answer:
Verified
Q20: Monitoring,as an activity,should be kept distinct from
Q21: In earned value Analysis,the 0 - 100
Q22: In earned value Analysis,EAC refers to the
Q23: In earned value analysis,(EV / AC)(EV /
Q24: If CPI = 1.05,then _ is favorable.
A)time
Q26: If EV = $500,AC = $475,PV =
Q27: If EV = $500,AC = $450,PV =
Q28: There are several conventions used to aid
Q29: In earned value analysis,the _ is computed
Q30: If EV = $500,AC = $475,PV =