In earned value Analysis,the 0 - 100 percent rule allows __________.
A) 100 percent credit before starting work and 0 percent credit after the completion
B) 0 percent credit when work begins and 100 percent credit when the project is complete
C) 0 percent credit when work begins and 100 percent credit at completion of the activity
D) 0 percent credit at completion of the activity and 100 percent credit at formal acceptance during scope verification
Correct Answer:
Verified
Q16: What is the relationship between management level
Q17: The project control process should be viewed
Q18: The best sources of items to be
Q19: _ is collecting,recording,and reporting information concerning any
Q20: Monitoring,as an activity,should be kept distinct from
Q22: In earned value Analysis,EAC refers to the
Q23: In earned value analysis,(EV / AC)(EV /
Q24: If CPI = 1.05,then _ is favorable.
A)time
Q25: There are several conventions used to aid
Q26: If EV = $500,AC = $475,PV =
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents