There are several conventions used to aid in estimating percent completion.Match each rule with its description.
A)50-50 rule
B)0-100 percent rule
C)Critical input use
D)Proportionality
1)This commonly used rule is also based on percentages,but uses time (or cost)as the critical input.
2)This rule assigns task progress according to the amount of an important input that has been used.
3)This rule allows no credit for work until the task is complete.
4)Fifty percent completion is assumed when the task is begun,and the remaining 50 percent when the work is complete.
Correct Answer:
Verified
Q43: Suggest some practical measures that can be
Q44: Alderton suggests telltale signs of project trouble.Match
Q45: When using earned value analysis,identify the three
Q46: Describe the three common difficulties in designing
Q47: List the four conventions used to aid
Q49: ST-AT =
A)TV
B)EV
C)CV
D)SV
Q50: Identify some of the benefits when timely
Q51: Conceptually,EAC represents the amount spent to date
Q52: List and describe five telltale signs of
Q53: ETC + AC = _.
A)BAC
B)EAC
C)SPI
D)CPI
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents