What is the latest that activity B can start if A lasts 35 days,B lasts 5,days C lasts 6 days,and D lasts 7 days?
A) 35
B) 36
C) 40
D) 41
Correct Answer:
Verified
Q26: Construction of the cattery could be
Q27: Construction of the cattery could be
Q37: The tablet unearthed by the archaeologist
Q40: The tablet unearthed by the archaeologist
Q41: _ is a technique to shorten the
Q42: A seven activity project has the activity
Q42: The longest path in a network from
Q44: How many days can this project be
Q49: A forward pass through a network is
Q58: Activities on the critical path may have