A seven activity project has the activity durations (in weeks) and costs shown in the table.The project manager has an overall budget of $20,000,what is the fastest completion time possible?
A) 29 weeks
B) 28 weeks
C) 27 weeks
D) 26 weeks
Correct Answer:
Verified