A project is composed of 6 activities that have durations and precedence requirements shown in the table.Which of these activities is NOT on the critical path?
A) A
B) B
C) C
D) D
Correct Answer:
Verified
Q20: The best use of a Gantt chart
Q20: In the project definition phase, project planners
Q21: What is the latest that activity D
Q22: This Gantt chart can be used to
Q28: Crashing a project refers to the technique
Q30: Construction of the cattery could be
Q33: The tablet unearthed by the archaeologist
Q41: The earliest start time of an activity
Q47: The earliest finish time is calculated by
Q53: A critical path is composed entirely of