A project team assesses their primary risk factor's probability of failure with a maturity risk of 0.3,a complexity risk of 0.7,and a dependency risk of 0.8.The probability of failure is:
A) Less than or equal to 0.3.
B) Greater than 0.3 but less than or equal to 0.55.
C) Greater than 0.56 but less than or equal to 0.89.
D) Greater than or equal to 0.9.
Correct Answer:
Verified
Q26: With a maturity risk of 0.3,a complexity
Q27: A project under strict terms and conditions
Q28: This scenario best describes a workaround:
A)Responding to
Q29: The inability of a company to accurately
Q30: A method for conducting risk factor identification
Q32: A company developing a brand-new technology that
Q33: The house had almost been framed when
Q34: A project team assigns probabilities of 0.1,0.2,and
Q35: The exposure a firm opens itself to
Q36: Workarounds are a response to project risk
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents