The firm set aside a little extra money just in case an unforeseen element of cost pushed the project beyond what they had budgeted.This extra money is called:
A) A rainy day fund.
B) A contingency reserve.
C) An escalation clause.
D) A sinking fund.
Correct Answer:
Verified
Q71: The European Association for Project Management has
Q72: The act of pairing a junior project
Q73: What is the relationship between a project's
Q74: One approach to risk mitigation is simply
Q75: What are the four alternatives a project
Q77: The expected cost of an item that
Q78: Each project team member had a backup
Q79: You have agreed to paint your neighbor's
Q80: Contingency reserves require a construction company to
Q81: How do mentoring and cross-training mitigate risk?