What Is the Late Finish Time for Activity D Given

Question 60

Multiple Choice

What is the late finish time for Activity D given the activity times and precedence requirements shown in the table?  Activity  Time  Predecessor  A 5B7C8 A D7 A E4 BF8C,DG9E,FH7G\begin{array} { | l | l | l | } \hline \text { Activity } & \text { Time } & \text { Predecessor } \\\hline \text { A } & 5 & -- \\\hline B & 7 & -- \\\hline \mathrm { C } & 8 & \text { A } \\\hline \mathrm { D } & 7 & \text { A } \\\hline \mathrm { E } & 4 & \mathrm {~B} \\\hline \mathrm { F } & 8 & \mathrm { C } , \mathrm { D } \\\hline \mathrm { G } & \mathrm { 9 } & \mathrm { E } , \mathrm { F } \\\hline \mathrm { H } & 7 & \mathrm { G } \\\hline\end{array}


A) 14
B) 13
C) 12
D) 11

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents