A Project Has the Precedence Requirements and Activity Durations Shown

Question 61

Multiple Choice

A project has the precedence requirements and activity durations shown in the table.After he draws the network,the project manager decides that activities H and I can be represented by a hammock activity.What are the early start and late finish times associated with this hammock activity?  Tirne  Predecessor A7B8 AC13 BD8CE7 AF6EG6 AH11GI12HJ14D,F,I\begin{array} { | l | l | l | } \hline & \text { Tirne } & \text { Predecessor } \\\hline \mathrm { A } & 7 & \\\hline B & 8 & \mathrm {~A} \\\hline \mathrm { C } & 13 & \mathrm {~B} \\\hline \mathrm { D } & 8 & \mathrm { C } \\\hline \mathrm { E } & 7 & \mathrm {~A} \\\hline \mathrm { F } & \mathrm { 6 } & \mathrm { E } \\\hline \mathrm { G } & 6 & \mathrm {~A} \\\hline \mathrm { H } & 11 & \mathrm { G } \\\hline \mathrm { I } & 12 & \mathrm { H } \\\hline \mathrm { J } & 14 & \mathrm { D } , \mathrm { F } , \mathrm { I } \\\hline\end{array}


A) 13,36
B) 13,24
C) 24,36
D) 7,36

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents