A project has the precedence requirements and activity durations shown in the table.After he draws the network,the project manager decides that activities H and I can be represented by a hammock activity.What are the early start and late finish times associated with this hammock activity?
A) 13,36
B) 13,24
C) 24,36
D) 7,36
Correct Answer:
Verified