Question 21
True/False
Preceding activities are those that must occur before others can be done.
Question 22
Multiple Choice
An activity has an optimistic time estimate of 25 days,a most likely estimate of 29 days,and a pessimistic estimate of 34 days.What is the expected duration of the activity?
Question 23
Multiple Choice
The length of time expected to complete an activity assuming that its development proceeds normally is called the:
Question 24
Multiple Choice
An activity has an optimistic time estimate of 17 days,a most likely estimate of 22 days,and a pessimistic estimate of 32 days.What is the expected duration of the activity?
Question 25
Multiple Choice
Project Test Bank is composed of activities we will refer to as A,B,C,and D for convenience (and lack of creativity) .Durations and precedence requirements are shown in the table.Each of these activities can be conveniently laddered into two sub-activities of equal duration.The first half of each activity serves as the predecessor to its second half and the first half of the original following activity.What is the expected completion time of the laddered project?
Activity
Length
Predecessor
A
10
−
−
B
18
A
C
14
A
D
20
B, C
\begin{array} { | l | l | l | } \hline \text { Activity } & \text { Length } & \text { Predecessor } \\\hline \text { A } & 10 & -- \\\hline B & 18 & \text { A } \\\hline \mathrm { C } & 14 & \text { A } \\\hline \mathrm { D } & 20 & \text { B, C } \\\hline\end{array}
Activity
A
B
C
D
Length
10
18
14
20
Predecessor
−
−
A
A
B, C
Question 26
True/False
At a merge point in a forward pass,the largest preceding early finish becomes the early start for that node.
Question 27
Multiple Choice
Project Test Bank is composed of activities we will refer to as A,B,C,and D for convenience (and lack of creativity) .Durations and precedence requirements are shown in the table.Each of these activities can be conveniently laddered into two sub-activities of equal duration.The first half of each activity serves as the predecessor to its second half and the first half of the original following activity.What is the expected completion time of the laddered project?
Activity
Length
Predecessor
A
10
−
−
B
18
A
C
14
A
D
20
B, C
\begin{array} { | l | l | l | } \hline \text { Activity } & \text { Length } & \text { Predecessor } \\\hline \text { A } & 10 & -- \\\hline B & 18 & \text { A } \\\hline C & 14 & \text { A } \\\hline D & 20 & \text { B, C } \\\hline\end{array}
Activity
A
B
C
D
Length
10
18
14
20
Predecessor
−
−
A
A
B, C
Question 28
Multiple Choice
The variance of an activity is given by:
Question 29
Multiple Choice
An activity has a pessimistic time that is four times as long as its most likely time and six times as long as its optimistic time.If the activity variance is 12,what is the expected time?