An important departure from traditional project management is that critical chain project management logic:
A) Changes from a late finish to an early start approach.
B) Factors in the effects of resource contention.
C) Adjusts expected activity durations to reflect a 95% probability of completion on time.
D) Creates a separate safety margin for each activity in the project.
Correct Answer:
Verified
Q44: What is the difference between the critical
Q45: Your boss catches you at the water
Q46: Alexander Demetrius Dickson,ADD to his friends,has three
Q47: Your next project consists of 10 consecutive
Q48: List any three criticisms of critical chain
Q50: The Central Limit Theorem states that if
Q51: Successful implementation of CCPM depends on first:
A)Identifying
Q52: A project consists of four activities
Q53: A project consists of four activities
Q54: What is aggregated buffer and how can
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents