Your next project consists of 10 consecutive 8-day activities,each estimated by a different worker in your organization.Note that the estimators have not yet added any buffer to the 8-day figure.Your organizational culture dictates that you add your own safety margin of 30% into your estimates.The new project manager has just completed an excellent course in project management offered at the local university.When the first project meeting begins,he dazzles you with his wit and sophistication.You are considerably less charmed when he reveals that he has an exciting new technique for managing projects.He adheres to critical chain project management ideas and plans to create an overall project safety buffer after trimming the safety buffers from each of the 10 activities.How much closer has the project deadline moved?
A) 12 days
B) 6 days
C) 18 days
D) 9 days
Correct Answer:
Verified
Q42: Which of the following statements about CCPM
Q43: What are the five steps behind the
Q44: What is the difference between the critical
Q45: Your boss catches you at the water
Q46: Alexander Demetrius Dickson,ADD to his friends,has three
Q48: List any three criticisms of critical chain
Q49: An important departure from traditional project management
Q50: The Central Limit Theorem states that if
Q51: Successful implementation of CCPM depends on first:
A)Identifying
Q52: A project consists of four activities
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents