A production line is to be designed for a job with three tasks.The task times are 0.6 minutes,1.8 minutes,and 1.2 minutes.If the necessary cycle time is 1.2 minutes per unit,what is the theoretical minimum number of workstations?
A) 2.0
B) 3.0
C) 3.6
D) 4.0
E) None of the choices are correct.
Correct Answer:
Verified