A production line is to be designed for a job with three tasks.The task times are 0.5 minutes,1.8 minutes,and 1.1 minutes.If the necessary cycle time is 1.0 minutes per unit,what is the actual minimum number of workstations possible?
A) 1
B) 2
C) 3
D) 4
E) None of the choices are correct.