A production cell uses 240 pounds of plastic resin each 8-hour day.Resin is transported in drums that hold 100 pounds each.The material is obtained from a nearby supplier,and has a 12-hour waiting time.A safety factor of .15 has been assigned to this cell.What is the optimum number of containers to support this operation?
Correct Answer:
Verified
D = 240/8 = 30...
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q66: The basic objective for operating with low
Q73: The Four Star Publishing Company uses sixty
Q74: Which of the following contributes to the
Q75: Which of the following is a characteristic
Q76: Material requirements planning (MRP)is an example of
Q77: Which of the following are potentially negative
Q79: With regard to suppliers,JIT systems typically involve:
A)
Q80: The All Seasonings Company uses 3,200 glass
Q81: A production system uses kanban cards to
Q82: With regard to suppliers,JIT systems typically require:
A)delivery
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents