Using the product-tree shown,determine the following:
(i)the quantity of component K that will be needed to assemble 80 units of P,assuming no on-hand inventory exists.
(ii)the quantity of component K needed to assemble 80 units of P,given on-hand inventory of 30 A's,50 B's and 20 C's.
Correct Answer:
Verified