In PERT, the expected project duration will never exceed the expected duration of the critical path.
Correct Answer:
Verified
Q26: The standard deviation of the critical path
Q32: Activities not on the critical path have
Q40: The total cost of crashing any one
Q41: Shortening activity durations is called:
A)Expediting
B)Crashing
C)Vendor management
D)Null nodes
E)Trade-off
Q42: The advantage(s) a precedence diagram has over
Q44: A sequence of activities that leads from
Q45: Concerning PERT and CPM:
A)These are two different
Q46: To _ an activity means to shorten
Q47: Project management differs from management of more
Q48: In a project network the critical path