The advantage(s) a precedence diagram has over a Gantt chart is(are) :
A) its ability to reveal relationships among activities.
B) it can easily show networks.
C) (a) and (b) .
D) its simplicity.
E) all of the above.
Correct Answer:
Verified
Q26: The standard deviation of the critical path
Q29: Slack time is equal to LS-ES or
Q32: Activities not on the critical path have
Q40: The total cost of crashing any one
Q41: Shortening activity durations is called:
A)Expediting
B)Crashing
C)Vendor management
D)Null nodes
E)Trade-off
Q43: In PERT, the expected project duration will
Q44: A sequence of activities that leads from
Q45: Concerning PERT and CPM:
A)These are two different
Q46: To _ an activity means to shorten
Q47: Project management differs from management of more
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents