Activity 4-5 in a network diagram has an optimistic time estimate of five days, a most likely time estimate of seven days, and a pessimistic time estimate of 10 days.Its expected time is approximately:
A) 5
B) 6
C) 7
D) 8
E) 9
Correct Answer:
Verified