Question 61
Essay
What is the difference between a baseline Gantt chart and a Tracking Gantt chart?
Question 62
True/False
All scope changes that result in increased costs should be avoided.
Question 63
True/False
The best method for assigning costs to the baseline under this rule is to establish frequent checkpoints over the duration of the work package and assign completion percentages in dollar terms.
Question 64
True/False
Overhead costs and profit are typically included in the project baseline.
Question 65
True/False
An undesirable schedule variance indicates that the project is running behind schedule.
Question 66
True/False
The rule of using subjective estimated percent complete in combination with hard, tangible monitoring points works well on long-duration activities that can be broken into short discrete work packages.