Essay

Activity C is directly preceded by two activities,activity A and activity B.Activity A has an expected time of five and early start time of six.Activity B has an expected time of seven and an early start time of seven.Activity C has an expected time of ten.What is the early start for activity C?
Activity A,early finish is 6 + 5 = 11.
Activity B,early finish is 7 + 7 = 14.
The early start for Activity 7 is the larger of the two early finish times; so the time is 14.