Draw a network diagram using the AON convention for the following project.
Activity A has a duration of 4 days and no predecessor.
Activity B has a duration of 2 days and has A as a predecessor.
Activity C has a duration of 2 days and has A as a predecessor.
Activity D has a duration of 3 days and has B as a predecessor.
Activity E has a duration of 4 days and has C as a predecessor.
Activity F has a duration of 1 day and has D and E as predecessors.
Correct Answer:
Verified
Q65: List the paths for the following network
Q66: Determine the amount of slack in each
Q67: Identify and describe the four parameters used
Q68: All the following activities are on the
Q69: Activity C is directly preceded by two
Q70: Compute the slack for the following project.
Activity
Q71: If an activity has an optimistic time
Q72: Identify and describe how leadership can impact
Q73: Identify four broad categories of risk associated
Q75: An activity with a duration of 8
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents