An activity with a duration of 8 days has an early start time of 25.Another activity has a duration of 5 days and an early start time of 25 days.Both activities precede activity M.Activity M has a duration of 4 days.What is the early start time for activity M?
Correct Answer:
Verified
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q65: List the paths for the following network
Q66: Determine the amount of slack in each
Q67: Identify and describe the four parameters used
Q68: All the following activities are on the
Q69: Activity C is directly preceded by two
Q70: Compute the slack for the following project.
Activity
Q71: If an activity has an optimistic time
Q72: Identify and describe how leadership can impact
Q73: Identify four broad categories of risk associated
Q74: Draw a network diagram using the AON
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents